Rapidus 2nm SRAM Yield Reportedly Zero, Putting FY2027 Mass Production Target Under Pressure
Rapidus 2纳米SRAM良率据报为零,2027财年量产目标承压
据彭博社报道、TechNews转述,日本晶圆代工厂Rapidus采用环绕式闸极(GAA)架构的2纳米制程,未能在2026年夏季达成SRAM功能单元的关键开发里程碑,目前SRAM良率仍为0%。北海道千岁市IIM-1晶圆厂还传出无尘室微粒污染问题,使原定2027财年下半年量产的目标增添变数。
Rapidus成立于2022年,技术开发主要依赖IBM的2纳米制程合作。2025年7月,执行长小池淳义曾宣布IIM-1厂已成功制造出具预期电气特性的2纳米GAA晶体管。但单颗晶体管能运作,与整合成可用的高密度芯片是不同门槛;SRAM阵列高度规律,任何微小制程偏差都可能造成读写失效,因此SRAM良率常被视为评估先进制程整合能力的重要指标。
作为对照,台积电N2的256Mb SRAM测试晶片良率在2023年4月突破50%,2024年4月超过90%。Rapidus仍强调按原定计划,在2027财年下半年、即最迟2028年3月底前启动量产。不过启动量产并不等于达到稳定的大规模量产,在此之前仍需完成SRAM功能验证、大型阵列测试、良率提升与制程认证等阶段。
Bloomberg reported, as relayed by TechNews, that Japanese foundry Rapidus's 2-nanometer process using a gate-all-around (GAA) architecture failed to meet a key development milestone for SRAM functional units in summer 2026, and that its SRAM yield remains 0%. The IIM-1 fab in Chitose, Hokkaido, has also been reported to have a cleanroom particle contamination problem, adding uncertainty to the original target of mass production in the second half of fiscal 2027.
据彭博社报道、TechNews转述,日本晶圆代工厂Rapidus采用环绕式闸极(GAA)架构的2纳米制程,未能在2026年夏季达成SRAM功能单元的关键开发里程碑,目前SRAM良率仍为0%。北海道千岁市IIM-1晶圆厂还传出无尘室微粒污染问题,使原定2027财年下半年量产的目标增添变数。
Rapidus was founded in 2022, and its technology development mainly depends on 2-nanometer process cooperation with IBM. In July 2025, CEO Atsuyoshi Koike announced that the IIM-1 fab had successfully manufactured 2-nanometer GAA transistors with the expected electrical characteristics. However, a single working transistor and integration into a usable high-density chip are different thresholds; SRAM arrays are highly regular, and any tiny process deviation may cause read/write failure, so SRAM yield is often regarded as an important indicator for assessing the integration capability of advanced processes.
Rapidus成立于2022年,技术开发主要依赖IBM的2纳米制程合作。2025年7月,执行长小池淳义曾宣布IIM-1厂已成功制造出具预期电气特性的2纳米GAA晶体管。但单颗晶体管能运作,与整合成可用的高密度芯片是不同门槛;SRAM阵列高度规律,任何微小制程偏差都可能造成读写失效,因此SRAM良率常被视为评估先进制程整合能力的重要指标。
By comparison, the yield of TSMC's N2 256Mb SRAM test chip exceeded 50% in April 2023 and 90% in April 2024. Rapidus still emphasizes that, according to the original plan, it will start mass production in the second half of fiscal 2027, or by the end of March 2028 at the latest. However, starting mass production does not equal achieving stable large-scale mass production; before that, it still needs to complete stages such as SRAM functional verification, large-array testing, yield improvement, and process certification.
作为对照,台积电N2的256Mb SRAM测试晶片良率在2023年4月突破50%,2024年4月超过90%。Rapidus仍强调按原定计划,在2027财年下半年、即最迟2028年3月底前启动量产。不过启动量产并不等于达到稳定的大规模量产,在此之前仍需完成SRAM功能验证、大型阵列测试、良率提升与制程认证等阶段。